2010/12/22 水電,木作,輕隔間,網路弱電 | Electrical , Carpentry, Light Steel Frame & Network Cabling Work

現場監工日誌 On-site supervising report


本日進場工種及工作摘要 / Workers & Job Summary
水電 6 人: 網路插座線路打佈管工程(立面佈管),插座及網路出線盒定位。
 6 Electrician: Laying communication cable and electrical wire pipes (vertical pipes on walls); Electrical and network outlet box positioning.

泥作 5 人: 水電打溝佈管溝槽修補填平,Training Room 地面墊高整平。
5 Cement Workers: Resurfacing of ground channels previously cut and drilled by electricians to lay pipes; Training Room raised ground cement surfacing work.



輕隔間 3 人: 部分隔間及封板修改補強。
3 Light Steel Frame Workers: Modifications on some partition walls.

若電網路 4 人: 網路弱電管路及線路佈設。
4 Network Cabling Workers: Network pipes and cable routing work.

木作 6 人: 門框及玻璃框立框,門片貼皮準備。
6 Carpenters: Wooden door frame fix-up into position; Wooden glass frame fix up.




現場施工細節照片 / Photos
Training Room ground resurfacing work

Wooden door frame fix into position

Electrical and network outlet box positioning

Laying networking cable

Wooden door plank