2010/12/17 輕隔間,水電,空調 | Light Steel Frame Wall, Electrical and Air Conditioning Works

現場監工日誌 On-site supervising report


本日進場工種及工作摘要 / Workers & Job Summary
水電 4 人:現有線路查修整理; 新設迴路佈線,開關插座盒定位,佈線溝槽標示。
5 Electrician: Current wiring check and renewal; New circuit wiring; Plug box installation; Ground wiring routing channels indication.

輕鋼架 5 人: 輕隔間牆骨架安裝及石膏板單面封板,局部隔音棉固定。
7 Light Steel Frame Workers: Partition wall light steel frame positioning; Gypsum board stapling on one side; Insulating material installation.

空調 4 人: 舊有管線檢查,舊有未利用管線拆除。
4 Air Conditioning Technician: Original A/C system check and abandoned pipes and ducts removal.



現場施工細節照片 / Photos
Wiring channel indication

Abandoned A/C pipes removal

Electrical plug box positioning


Abandoned A/C pipes

Electrical wiring check (IT. Room)