本日持續進行前日的相關工程,隔間及水電管線測試更新。
Training Room 活動隔音牆進行吊軌定位及固定工作。

Workers will continue with previous day's work which include steel frame wall partition and electrical systems check and wirin.
Overhead railing for Training Room sliding walls will also begin installation work today.

Progres on wall partition (entrance)

Progress on wall partition (west wing)

Progress on wall partition (west wing)

Progress on wall partition (training room and entrance)

Training room sliding wall overhead railing installation work

Progress on wall partition (IT Room)