2010/12/28 水電,輕隔間,油漆 ,木作,空調 | Electrical, Light Steel Frame , Paint, Carpentry & Air Conditioning

現場監工日誌 On-site supervising report


本日進場工種及工作摘要 / Workers & Job Summary
水電 5 人: 電線佈設,配電盤定位
5 Electrician: Laying communication cable and electrical wires; Circuit switch panels positioning.

輕隔間 4 人: 部分隔間及封板修改補強,第二面封板作業。
4 Light Steel Frame Workers: Modifications on some partition walls; Put up second side of gypsum dry board on partition walls.

油漆 2 人: 木製門框批土。
2 Painters: Wooden door frame plastering work.

木工 4 人: 門片貼皮,門片定位。
4 Carpenters: Fix up surface material for doors; Doors positioning.

空調 6 人:室內機吊掛,電路配線,冰水管佈設。
6 A/C Technicians: Indoor A/C fan unit positioning; electrical and control wirings; cool water chiller pipes installation.



現場施工細節照片 / Photos
Entrance hallway overhead wooden light box mock up (previous day's work)

Fixing up hinges for the doors

Door frame plastering work

Partition walls insulation installed and ready for putting up gypsum dry boards.