本日進場工種及工作摘要 / Workers & Job Summary
水電 5 人: 電線佈設,配電盤定位
5 Electrician: Laying communication cable and electrical wires; Circuit switch panels positioning.
輕隔間 4 人: 部分隔間及封板修改補強,第二面封板作業。
4 Light Steel Frame Workers: Modifications on some partition walls; Put up second side of gypsum dry board on partition walls.
油漆 2 人: 木製門框批土。
2 Painters: Wooden door frame plastering work.
木工 4 人: 門片貼皮,門片定位。
4 Carpenters: Fix up surface material for doors; Doors positioning.
空調 6 人:室內機吊掛,電路配線,冰水管佈設。
6 A/C Technicians: Indoor A/C fan unit positioning; electrical and control wirings; cool water chiller pipes installation.
現場施工細節照片 / Photos
Entrance hallway overhead wooden light box mock up (previous day's work) |
Fixing up hinges for the doors |
Door frame plastering work |
Partition walls insulation installed and ready for putting up gypsum dry boards. |