2010/12/24 水電,木作,輕隔間,油漆 ,空調| Electrical , Carpentry, Light Steel Frame , Paint & Air Conditioning

現場監工日誌 On-site supervising report


本日進場工種及工作摘要 / Workers & Job Summary
水電 6 人: 網路插座線路打佈管工程(立面佈管),插座及網路出線盒定位,配電盤定位
 6 Electrician: Laying communication cable and electrical wire pipes (vertical pipes on walls); Electrical and network outlet box positioning; Circuit switch panels positioning.

輕隔間 3 人: 部分隔間及封板修改補強。
3 Light Steel Frame Workers: Modifications on some partition walls.

木作 6 人: 門框及玻璃框立框,門片貼皮準備。
6 Carpenters: Wooden door frame fix-up into position; Wooden glass frame fix up.



油漆 2 人: 木製門框批土。
2 Painters: Wooden door frame plastering work.


空調 5 人:冰水管移除及佈設,電路管線配管。
5 A/C Technicians: Old chiller pipes removal and new chiller pipes installation; electrical and control wirings pipes positioning.




現場施工細節照片 / Photos
Door frame plastering work

A/C cool water chiller pipes (parts)

A/C indoor fan units (parts)

A/C cool water chiller pipes installation




Akuma Design
Johnny Shen